Infrastructure Projects - Construction Technology
A Practical Guide to Construction Techniques and Practice
|
Here's a detailed view of the soil nail. A high-strength steel rod is being installed and you can see that the drill bit has been attached to the end of the rod. That's an efficient way of doing this, but the drill bit is actually lost in the hole. These are shallow rods and called soil nails. A similar arrangement is used to install earth anchors. They are much deeper and much higher capacity, and they would be attached to a whaler and would carry a much higher load. This is kind of a light version of a soil anchor. When it's used this way, it's called a soil nail.
This is a good view of the general excavation. They've pretty much gone down to the bottom of the footing, and they've run into groundwater. The groundwater on the contract drawings was shown to be below the bottom of the footing, but, unfortunately, they are running into it in the course of the excavation.
To overcome that unexpected high water table, they put in several local wells. They are drilled in and filled with crushed stone. Then, a submersible pump is installed in each one. They proved to be very effective and were able to manage that high water table. |
![]() They also made a judgment now that the footing is underway. They decided to proceed with shifting the traffic up above and removing one half of the bridge. The original plan was to wait until this abutment was constructed as far as possible, but I think they see their very limited gains in using that original concept, and now want to carry out the abutment construction and the removal of one half of the bridge simultaneously. That will certainly shorten the overall duration. I have some video showing that traffic shift. After the morning peak, traffic can be contained into a single lane and that's what's being done here. That frees up the adjoining lane. At this point, they are delivering a impact attenuator. That's going to be used the temporarily, as the traffic is shifted. With one lane closed, you can now extend the concrete barriers into that closed lane and go as far as you can with them. You attach this impact attenuator to the end of the barriers, and then you can redirect the traffic into the new configuration.
These trucks will do the striping on the day of the traffic shift. You have to be able to put down the permanent striping pattern. This is very critical, because the traffic will be in a new configuration, and they will be very much guided by the new painted lines. If the new lines are in conflict with some existing line, those existing lines need to be removed. The impact attenuator is now going to be installed to protect the end of that concrete barrier. Obviously, you need to protect the traffic against that exposed end. At that point, traffic can be shifted onto the new alignment and there will be no traffic on the old roadway, so that the barriers can be reconfigured to accommodate the new traffic alignment. |